Engineering keeps missing dates. What can a CEO do about it?

Short answer

Start by finding out which kind of miss it is: a date set without the team, scope that grew, too much in progress, work that waited on someone else, or an estimate that was a hope. Each has a different fix, and several are yours: fewer priorities at once, dates agreed with engineering present, and forecasts given as ranges.

Five reasons dates slip, and who can fix each

PatternHow it showsWho can change it
The date came before the planA sales or board date was set, then engineering was toldThe CEO: agree dates with engineering present
Scope grew quietly“While we are there” additions, none traded for timeThe CEO and product: trade scope for date, out loud
Too much at onceEverything is in progress and little is finishedThe CEO: rank the priorities and stop some
Work waitsQueues for review, decisions, other teams or suppliersThe CTO: find the queues and remove them
Estimates were hopesOne date, no range, no reference to past deliveryThe CTO: forecast from what the team has actually delivered

The first three are leadership decisions. No amount of engineering skill fixes them from below.

What you can change this month

  1. Ask for the last five missed dates and the reason for each, in one line. The pattern usually shows at once.
  2. Cut the number of things in progress. Two finished beats six started.
  3. Stop giving customers dates that engineering has not seen.
  4. Ask for forecasts as a range with a confidence, and what would narrow it.
  5. Release smaller pieces sooner, so that a slip costs weeks instead of quarters.

What makes the next date worse

Pressure, longer hours and more people are the instinctive responses. Pressure produces optimistic estimates. Long hours produce defects that surface later. New people take time from the people who are already behind.

Avoid asking for a recovery plan with the original date fixed and nothing removed. You will get the plan, and you will miss the date.

When the pattern continues

If priorities are stable and dates are agreed together, and work still slips, the constraint is inside engineering: how work is sliced, reviewed, tested and released. That can be diagnosed by following a few recent pieces of work from idea to production and noting where each one waited.

How to diagnose slow software delivery

One particularly large core feature had been causing difficulties for months; James stepped in and completed the majority of the work within about three days.

Ivan Finn Founder at AdsDroid and Adigy.ai · James’s client

Read the recommendation in context

Related questions

Should we add a project manager?

Only if coordination is the constraint. A project manager can make slips visible sooner, but cannot fix unclear priorities or work that is sliced too large.

Are estimates worth having at all?

Yes, as forecasts that are updated, not promises extracted once. The useful questions are how confident the team is and what would change that.

Is this a sign I need a new CTO?

Not on its own. Missed dates with early warning and clear reasons are a planning problem you can fix together. Missed dates that arrive as surprises, repeatedly, are a different signal.